Overview of next 6 weeks

  • May 6 - June 8, 2011 : expect some disruptions
  • A long trench for water and sewar lines will be dug witihn 300' of NYSBC
  • Possible large disruption for weeks of May 9-13 and June 6-8, when rock excavation will occur
  • Expect minor disruption from heavy equipment from April 26 - June 8 : surface soul removal
  • Work will be done all day, morning until night, in order to get entire job done quickly

Construction schedule (updated weekly)

June 2026
  01 02 03 04 05 06
07 08 09 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30        

July 2026
      01 02 03 04
05 06 07 08 09 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31  

  • 26 Apr 2011 - 29 Apr 2011 - soil removal, possible disruption from heavy equipment
  • 2 May 2011 - 6 May 2011 - soil removal, possible disruption from heavy equipment
  • 9 May 2011 - 13 May 2011 - expect disruption from heavy rock removal
  • 16 May 2011 - 20 May 2011 - soil removal, possible disruption from heavy equipment
  • 23 May 2011 - 27 May 2011 - soil removal, possible disruption from heavy equipment
  • 30 May 2011 - 3 Jun 2011 - soil removal, possible disruption from heavy equipment
  • 6 Jun 2011 - 8 Jun 2011 - expect disruption from heavy rock removal

Previous information

  • March 2010 - Removal and sifting of rock pile has yet to begin- no disruptions anticipated - Normal (9-6) CEM working hours resumed until further notice
  • Construction from 7 am to 3:30 pm
  • General work times: 7am - 9 am ; 9:30 am - 11:30 am ; 12:30 pm - 3:00 pm
  • During construction hours, data collection impaired on cryo samples for TF20, J3200, J2100
  • 31 Jul 2009 -7 Sep 2009 Removal and sifting of rock pile - no disruptions anticipated - Normal (9-6) CEM working hours resumed until further notice
  • 22 Jun 2009 - 26 Jun 2009 - Digging into new rock, expect heavy disruption
  • week of 28 July: clearing of field behind NYSBC
  • 26 Aug 2008 : heavy construction scheduled to begin
  • 28 Jul 2008 - heavy construction / rock removal near building 7:00 am to 3:30 pm
  • 29 Jul 2008 - heavy construction / rock removal near building 7:00 am to 3:30 pm
  • 30 Jul 2008 - heavy construction / rock removal near building 7:00 am to 3:30 pm
  • 31 Jul 2008 - heavy construction / rock removal near building 7:00 am to 3:30 pm
  • 1 Aug 2008 - heavy construction / rock removal near building 7:00 am to 3:30 pm
  • 25 Sep 2008 - heavy construction set to begin
  • 4 Dec 2008 - Earliest day for construction to begin
  • 19 Jan 2009 - 23 Jan 2009 - Construction begins: Heavy excavation near NYSBC, set aside for testing
    • Testing of the microscopes will be taking place
    • Bookings for this week delayed until we determine the impact of the excavation

  • Set ALLOWTOPICVIEW =

-- BillRice - 24 Jul 2008

 
Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding this intranet, Send feedback