NYSBC Power SHutdown 9/16 - 9/19

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

Emergency Generator

Changed:
<
<
  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a fuel leak. This leak is actually a coolant leak..HO PENN states this is minor and will not imdead the operation of the generator for the shutdown...HO PENN is recommending however that the leak be attended to, this work is being scheduled for after the shutdown.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service. The service has been completed.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31. 9/14 MG. The fuel delivery has been arranged for 9/19.
>
>
  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a fuel leak. This leak is actually a coolant leak..HO PENN states this is minor and will not imdead the operation of the generator for the shutdown...HO PENN is recommending however that the leak be attended to, this work is being scheduled for after the shutdown.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service. The service has been completed.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31. 9/14 MG. The fuel delivery has been arranged for 9/19.
 

Emergency Generator

Safety Security

Starr: Will one guard be enough to provide suficient coverage, while power is out?

Changed:
<
<
  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCEPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.
>
>
  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCEPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.
 Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

Telephone System

Per Kris Halpern of PhoneExtra?, power down expansion unit, then main processor,Then UPS, power up the UPS, then main processor, then expansion unit. This system was backed up on 9/14.

NMR Facility Shutdown.

Changed:
<
<
  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.
>
>
  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.
 

Air compressor shudown.

Changed:
<
<
  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.
>
>
  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.
 

Water chiller.

Changed:
<
<
  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.
>
>
  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.
 
SHUTDOWN & RESTART LIST Place Permissions
HVAC    
Changed:
<
<
Air Compressor B level sound proof room wall switch MG
>
>
Air Compressor B level sound proof room wall switch MG
 
After cooler B level Sound proof room power switch on unit MG
Air drier B level wall mount by units MG


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

Changed:
<
<
  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.
>
>
  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.
 

Equipment Start Order

Computer services will be restored in the following order -
Changed:
<
<
  1. Network
  2. E-mail server
  3. Data Server
  4. SFTP Server
  5. DL380
  6. Accounting - Josh's PC starts first because of drive mappings.
  7. Administration & Office area
  8. Labs
  9. NYSBC Wireless
  10. Public Wireless
>
>
  1. Network
  2. E-mail server
  3. Data Server
  4. SFTP Server
  5. DL380
  6. Accounting - Josh's PC starts first because of drive mappings.
  7. Administration & Office area
  8. Labs
  9. NYSBC Wireless
  10. Public Wireless
 

GG original

Changed:
<
<
Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.
>
>
Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.
  I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

Changed:
<
<
  • Set ALLOWTOPICVIEW =
>
>
  • Set ALLOWTOPICVIEW =
 -- DhireshVyas - 13 Sep 2005
META FILEATTACHMENT attr="" comment="Starr Schedules for Shutdown weekend" date="1126881750" name="starr911918.pdf" path="starr911918.pdf" size="63877" user="JasperShahn" version="1.1"
Added:
>
>
META TOPICMOVED by="DavidCowburn" date="1182353933" from="Staff.ShutDown" to="Staffarchive.ShutDown"
 

Revision 1416 Sep 2005 - Main.JasperShahn

 Contents

NYSBC Power SHutdown 9/16 - 9/19

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a fuel leak. This leak is actually a coolant leak..HO PENN states this is minor and will not imdead the operation of the generator for the shutdown...HO PENN is recommending however that the leak be attended to, this work is being scheduled for after the shutdown.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service. The service has been completed.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31. 9/14 MG. The fuel delivery has been arranged for 9/19.

Emergency Generator

Safety Security

Starr: Will one guard be enough to provide suficient coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCEPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

Telephone System

Per Kris Halpern of PhoneExtra?, power down expansion unit, then main processor,Then UPS, power up the UPS, then main processor, then expansion unit. This system was backed up on 9/14.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

SHUTDOWN & RESTART LIST Place Permissions
HVAC    
Air Compressor B level sound proof room wall switch MG
After cooler B level Sound proof room power switch on unit MG
Air drier B level wall mount by units MG


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.

Equipment Start Order

Computer services will be restored in the following order -
  1. Network
  2. E-mail server
  3. Data Server
  4. SFTP Server
  5. DL380
  6. Accounting - Josh's PC starts first because of drive mappings.
  7. Administration & Office area
  8. Labs
  9. NYSBC Wireless
  10. Public Wireless

GG original Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =

-- DhireshVyas - 13 Sep 2005

Added:
>
>
META FILEATTACHMENT attr="" comment="Starr Schedules for Shutdown weekend" date="1126881750" name="starr911918.pdf" path="starr911918.pdf" size="63877" user="JasperShahn" version="1.1"
 

Revision 1314 Sep 2005 - Main.MichaelGoger

 Contents

NYSBC Power SHutdown 9/16 - 9/19

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a fuel leak. This leak is actually a coolant leak..HO PENN states this is minor and will not imdead the operation of the generator for the shutdown...HO PENN is recommending however that the leak be attended to, this work is being scheduled for after the shutdown.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service. The service has been completed.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31. 9/14 MG. The fuel delivery has been arranged for 9/19.

Emergency Generator

Safety Security

Starr: Will one guard be enough to provide suficient coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCEPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

Telephone System

Changed:
<
<
Per Kris Halpern of PhoneExtra?, power down expansion unit, then main processor, power up main processor, then expansion unit.
>
>
Per Kris Halpern of PhoneExtra?, power down expansion unit, then main processor,Then UPS, power up the UPS, then main processor, then expansion unit. This system was backed up on 9/14.
 

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

SHUTDOWN & RESTART LIST Place Permissions
HVAC    
Air Compressor B level sound proof room wall switch MG
After cooler B level Sound proof room power switch on unit MG
Air drier B level wall mount by units MG


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.

Equipment Start Order

Computer services will be restored in the following order -
  1. Network
  2. E-mail server
  3. Data Server
  4. SFTP Server
  5. DL380
  6. Accounting - Josh's PC starts first because of drive mappings.
  7. Administration & Office area
  8. Labs
  9. NYSBC Wireless
  10. Public Wireless

GG original Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =

-- DhireshVyas - 13 Sep 2005

Revision 1214 Sep 2005 - Main.JasperShahn

 Contents

NYSBC Power SHutdown 9/16 - 9/19

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a fuel leak. This leak is actually a coolant leak..HO PENN states this is minor and will not imdead the operation of the generator for the shutdown...HO PENN is recommending however that the leak be attended to, this work is being scheduled for after the shutdown.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service. The service has been completed.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31. 9/14 MG. The fuel delivery has been arranged for 9/19.
Added:
>
>

Emergency Generator

 

Safety Security

Starr: Will one guard be enough to provide suficient coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCEPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.
Added:
>
>

Telephone System

Per Kris Halpern of PhoneExtra?, power down expansion unit, then main processor, power up main processor, then expansion unit.

 

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

SHUTDOWN & RESTART LIST Place Permissions
HVAC    
Air Compressor B level sound proof room wall switch MG
After cooler B level Sound proof room power switch on unit MG
Air drier B level wall mount by units MG


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.

Equipment Start Order

Computer services will be restored in the following order -
  1. Network
  2. E-mail server
  3. Data Server
  4. SFTP Server
  5. DL380
  6. Accounting - Josh's PC starts first because of drive mappings.
  7. Administration & Office area
  8. Labs
  9. NYSBC Wireless
  10. Public Wireless

GG original Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =

-- DhireshVyas - 13 Sep 2005

Revision 1114 Sep 2005 - Main.MichaelGoger

 Contents

NYSBC Power SHutdown 9/16 - 9/19

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

Emergency Generator

  • Emergency generator has been load tested on 8/30.
Changed:
<
<
  • After the load test, there appears to have been a fuel leak.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31.
>
>
  • After the load test, there appears to have been a fuel leak. This leak is actually a coolant leak..HO PENN states this is minor and will not imdead the operation of the generator for the shutdown...HO PENN is recommending however that the leak be attended to, this work is being scheduled for after the shutdown.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service. The service has been completed.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31. 9/14 MG. The fuel delivery has been arranged for 9/19.
 

Safety Security

Starr: Will one guard be enough to provide suficient coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCEPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

SHUTDOWN & RESTART LIST Place Permissions
HVAC    
Air Compressor B level sound proof room wall switch MG
After cooler B level Sound proof room power switch on unit MG
Air drier B level wall mount by units MG


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.

Equipment Start Order

Computer services will be restored in the following order -
  1. Network
  2. E-mail server
  3. Data Server
  4. SFTP Server
  5. DL380
  6. Accounting - Josh's PC starts first because of drive mappings.
  7. Administration & Office area
  8. Labs
  9. NYSBC Wireless
  10. Public Wireless

GG original Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =
Changed:
<
<
-- DhireshVyas - 13 Sep 2005
>
>
-- DhireshVyas - 13 Sep 2005
Deleted:
<
<
 

Revision 1013 Sep 2005 - Main.DhireshVyas

 Contents

NYSBC Power SHutdown 9/16 - 9/19

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a fuel leak.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31.

Safety Security

Starr: Will one guard be enough to provide suficient coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCEPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

SHUTDOWN & RESTART LISTup Place Permissions
HVAC    
Air drier B level wall mount by units MG
Air Compressor B level sound proof room wall switch MG
After cooler B level Sound proof room power switch on unit MG


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.
Added:
>
>

Equipment Start Order

Computer services will be restored in the following order -
  1. Network
  2. E-mail server
  3. Data Server
  4. SFTP Server
  5. DL380
  6. Accounting - Josh's PC starts first because of drive mappings.
  7. Administration & Office area
  8. Labs
  9. NYSBC Wireless
  10. Public Wireless
  GG original Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =
Changed:
<
<
-- JasperShahn - 26 Aug 2005
>
>
-- DhireshVyas - 13 Sep 2005
Added:
>
>
 

Revision 907 Sep 2005 - Main.DavidCowburn

 Contents

NYSBC Power SHutdown 9/16 - 9/19

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a fuel leak.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31.

Safety Security

Starr: Will one guard be enough to provide suficient coverage, while power is out?

Changed:
<
<
  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCPTED DELIVERIES AND NO ACCEPTED MAIL.
>
>
  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCEPTED DELIVERIES AND NO ACCEPTED MAIL.
 
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

SHUTDOWN & RESTART LIST Place Permissions
HVAC    
Air Compressor B level sound proof room wall switch MG
After cooler B level Sound proof room power switch on unit MG
Air drier B level wall mount by units MG


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.

GG original Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

Revision 806 Sep 2005 - Main.DhireshVyas

 Contents

NYSBC Power SHutdown 9/16 - 9/19

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a fuel leak.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31.

Safety Security

Starr: Will one guard be enough to provide suficient coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

SHUTDOWN & RESTART LIST Place Permissions
HVAC    
Air Compressor B level sound proof room wall switch MG
After cooler B level Sound proof room power switch on unit MG
Air drier B level wall mount by units MG


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

Changed:
<
<
1. On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.

2. On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.

3. All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.

4. The following items will be taken offsite -

>
>
  • On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.
  • On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.
  • All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
  • The following items will be taken offsite -
    • Backup Tapes - including catalog.
    • Operating system drive from the Data Server
  • When power has been restored, we need to start a specific sequence of powering up the equipment.
Deleted:
<
<
i. Backup Tapes - including catalog. ii. Operating system drive from the Data Server

5. When power has been restored, we need to start a specific sequence of powering up the equipment.

  GG original Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

Revision 706 Sep 2005 - Main.DavidCowburn

 Contents

NYSBC Power SHutdown 9/16 - 9/19

Added:
>
>

ALL STAFF

It is expected that most HVAC and other circuits will go off 5 pm Friday. You should have all work cease before then, and leave the building. Only the on-schedule staff will then be permitted to enter before power is restored.

On Monday, it is expected that power will be restored before 9 am. This should be evident by restoration of the phone system. If power is NOT restored, only the on-schedule staff will be permitted to enter until power is restored.

 

Emergency Generator

  • Emergency generator has been load tested on 8/30.
Changed:
<
<
  • After the load test, there appears to have been a feul leak.
  • HO Penn will arrive 9/2 8 am to fix fueld leak and perform contract Major Service.
>
>
  • After the load test, there appears to have been a fuel leak.
  • HO Penn will arrive 9/2 8 am to fix fuel leak and perform contract Major Service.
 
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31.

Safety Security

Changed:
<
<
Starr: Will on guard be enough to provide suffiecent coverage, while power is out?
  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List".
  • We need to arrange for an analog phone to be run out to the gaurd desk.
  • We should arrange to have a small low power lamp run out to the guard desk to be powered off the generator.
>
>
Starr: Will one guard be enough to provide suficient coverage, while power is out?
  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List". THERE WILL BE NO ACCPTED DELIVERIES AND NO ACCEPTED MAIL.
  • Cell phone service only to be expected. Phones must be prepowered or repowered by car chargers. Do not assume any analog phone service.
  • Emergency battery lighting needs to be arranged for guard and on-station staff person.
 Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.
Added:
>
>
SHUTDOWN & RESTART LIST Place Permissions
HVAC    
Air Compressor B level sound proof room wall switch MG
After cooler B level Sound proof room power switch on unit MG
Air drier B level wall mount by units MG

 

Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

1. On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.

2. On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.

Changed:
<
<
3. All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent
>
>
3. All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.
Deleted:
<
<
damage from power spikes.
  4. The following items will be taken offsite - i. Backup Tapes - including catalog. ii. Operating system drive from the Data Server

5. When power has been restored, we need to start a specific sequence of powering up the equipment.

Changed:
<
<
Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server.
>
>
GG original
Added:
>
>
Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server. DC suggestion. Best to advise if mail is not delivered. Expected outage is Fri 5 pm through Mon noon, close to 72 h. Suggest email restoration is top restart item Monday and that backup not be used.
  I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

Revision 602 Sep 2005 - Main.DavidCowburn

 Contents

NYSBC Power SHutdown 9/16 - 9/19

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a feul leak.
  • HO Penn will arrive 9/2 8 am to fix fueld leak and perform contract Major Service.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31.

Safety Security

Starr: Will on guard be enough to provide suffiecent coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List".
  • We need to arrange for an analog phone to be run out to the gaurd desk.
  • We should arrange to have a small low power lamp run out to the guard desk to be powered off the generator.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.


Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

1. On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.

2. On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.

3. All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.

4. The following items will be taken offsite - i. Backup Tapes - including catalog. ii. Operating system drive from the Data Server

5. When power has been restored, we need to start a specific sequence of powering up the equipment.

Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

Revision 502 Sep 2005 - Main.DavidCowburn

 Contents

NYSBC Power SHutdown 9/16 - 9/19

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a feul leak.
  • HO Penn will arrive 9/2 8 am to fix fueld leak and perform contract Major Service.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31.

Safety Security

Starr: Will on guard be enough to provide suffiecent coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List".
  • We need to arrange for an analog phone to be run out to the gaurd desk.
  • We should arrange to have a small low power lamp run out to the guard desk to be powered off the generator.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.
Added:
>
>

Infotech

To prepare for the electrical shutdown, Infotech plans to take the following steps to ensure a smooth transition. Please feel free to add any comments.

1. On Thursday, Sept 15, start a full backup of the servers and office pcs to tape. The tapes will be taken offsite.

2. On Friday, Sept 16, initiate a shutdown of all the servers and network equipment. Call the T1 line provider to inform them of the situation.

 
Added:
>
>
3. All users will need to power off their PCs, a walkthrough will be required to ensure that all equipment is shut down and unplugged from outlets to prevent damage from power spikes.

4. The following items will be taken offsite - i. Backup Tapes - including catalog. ii. Operating system drive from the Data Server

5. When power has been restored, we need to start a specific sequence of powering up the equipment.

Normally a server attempts delivery of an e-mail for 72 hours, after which it is bounced back to the sender. Since the equipment will be powered off for more than 72 hours, to prevent messages sent to nysbc from being returned to the sender, Infotech will arrange for a mail backup service, where all mail addressed to nysbc will be held until the equipment is powered up. Once power has been restored, all messages will be forwarded to our mail server.

I would like to recommend that all outgoing messages contain a disclaimer stating the times that mailserver will be down and that messages will not be responded to for the time that the server is down.

The mailbackup service will not deliver messages to other accounts, so all the forwarders set up on the mail server will not work.

Regards,

Dhiresh.

 
  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

Revision 431 Aug 2005 - Main.JasperShahn

 Contents

NYSBC Power SHutdown 9/16 - 9/19

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a feul leak.
Changed:
<
<
  • HO Penn is being scheduled to address the leak and perform scheduled service.
  • MG contacted Metro fuel oil (718) 383-1400...We need to re-open the account before they will schedule a delivery... I suggest we do this with AMEX card so as to avoid the delays with credit checks.
>
>
  • HO Penn will arrive 9/2 8 am to fix fueld leak and perform contract Major Service.
  • MG contacted Metro fuel oil (718) 383-1400. JS reinstated account 8/31.
 

Safety Security

Starr: Will on guard be enough to provide suffiecent coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List".
  • We need to arrange for an analog phone to be run out to the gaurd desk.
  • We should arrange to have a small low power lamp run out to the guard desk to be powered off the generator.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

Revision 331 Aug 2005 - Main.MichaelGoger

 Contents

NYSBC Power SHutdown 9/16 - 9/19

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a feul leak.
  • HO Penn is being scheduled to address the leak and perform scheduled service.
Added:
>
>
  • MG contacted Metro fuel oil (718) 383-1400...We need to re-open the account before they will schedule a delivery... I suggest we do this with AMEX card so as to avoid the delays with credit checks.
 

Safety Security

Starr: Will on guard be enough to provide suffiecent coverage, while power is out?

  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List".
  • We need to arrange for an analog phone to be run out to the gaurd desk.
  • We should arrange to have a small low power lamp run out to the guard desk to be powered off the generator.

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

HVAC

York: Message to Mike McHugh? re controls and AHU shutdowns.

NMR Facility Shutdown.

  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.

  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

Revision 231 Aug 2005 - Main.MichaelGoger

 Contents

NYSBC Power SHutdown 9/16 - 9/19

Added:
>
>

Emergency Generator

  • Emergency generator has been load tested on 8/30.
  • After the load test, there appears to have been a feul leak.
  • HO Penn is being scheduled to address the leak and perform scheduled service.
 

Safety Security

Added:
>
>
Starr: Will on guard be enough to provide suffiecent coverage, while power is out?
  • Guard need to be instructed that no one be allowed in the building during the power outage unless they are the Special "Shutdown Access List".
  • We need to arrange for an analog phone to be run out to the gaurd desk.
  • We should arrange to have a small low power lamp run out to the guard desk to be powered off the generator.
 Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

Added:
>
>

HVAC

 York: Message to Mike McHugh? re controls and AHU shutdowns.
Changed:
<
<

subsub level topic

>
>

NMR Facility Shutdown.

Added:
>
>
  • Liq. He fills are scheduled for Tues. 9/13.
  • NMR operations by affiliate users is to cease by noon Fri. 9/16. All affiliates to be informed that data should be transfered before 2:00 p.m.. Data serever will not be available until Monday afternoon at the earliest. All samples should be removed from refigerator in Lab B-10.
  • All cryoprobes are to be warmed-up, process takes about 2 hours, cryoplatforms to be powered off.
  • Once cryoprobes are warm, consoles are to be shut down by normal proceedure...i.e. telnet spect/init 0, etc.
  • HP pc's to be shutdown and powered off.
  • All high purity He and back-up N2 cyclinders are to be closed.
  • The only components to remain running are the pumps and BMPC.

Air compressor shudown.

  • The timing of the air compressor shutdown is to be coordinated between the NMR and CEM facilities.
  • There are 3 components that need to be powered off, 1) compressor, 2) refigerated after-cooler, 3) air drier.

Water chiller.

  • The chiller and pump are to be powered down after the cryoprobes have been warmed-up.
 
  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

Revision 126 Aug 2005 - Main.JasperShahn

 Contents

NYSBC Power SHutdown 9/16 - 9/19

Safety Security

Briscoe: fax memo to be forwarded to central station. Anna will pass along info to technicians for callback 8/29.

ADT: Dan Kelly on vac. Call for sub on 9/26

York: Message to Mike McHugh? re controls and AHU shutdowns.

subsub level topic

  • Set ALLOWTOPICVIEW =

-- JasperShahn - 26 Aug 2005

 
Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding this intranet, Send feedback